Weston Avenue Reconstruction, Alderson Street Reconditioning, Summit Avenue Pavement Replacement, & Village of Weston Utilities Projects – STARTING  6/17/2024 with ROAD CLOSURES

Weston Avenue Reconstruction, Alderson Street Reconditioning, Summit Avenue Pavement Replacement, & Village of Weston Utilities Projects – STARTING  6/17/2024 with ROAD CLOSURES

These projects are cooperative joint projects between the Villages of Weston and Rothschild.  Both Village’s have been working on this project since 2022 and have been successful in being a recipient of a WisDOT MSID Grant in amount of rough $733,000 split evenly.  This $2.6M project has been awarded to Haas Sons, Inc. based out of Thorp, Wisconsin.   A compact round about will be constructed at the Weston and Alderson Street Intersection as part of the overall work.  The project will entail the full closure of segments of roadways at various stages to traffic.  Alternate routes of travel will need to be determined by the motorist.

In general, the project outline is as follows:

Weston Avenue Reconstruction.  The project limits are from Alderson Street on the west to Birch Street on the east.  This segment of roadway is proposed to be fully reconstructed as a two lane road with curb and gutter, dual 4-foot bike lanes and a multi-use pedestrian path on the south side of the roadway.

Alderson Street Reconstruction.  The project limits are from Summit Avenue on the north to Weston Avenue on the south.  This segment of roadway is proposed to have both water and sewer utility work completed under the jurisdiction of Weston.  The roadway will have new asphalt and curb and gutter replaced.

Summit Avenue Pavement Replacement.  The project limits are from Alderson Street on the east to Wall Street on the east.  This segment of roadway is proposed to have water utility work completed under the jurisdiction of Weston.  The roadway will also receive ditching and some storm sewer placement on the south side of the roadway only to improve drainage.   The roadway will be pulverized, and the pavement replaced at the same width as is existing.

Village of Weston Utilities.  This project encompasses Weston’s desire for new and reconstructed utility work and needs as part of the overall project.

The project schedule is as follows:

  1. The segment of Alderson Street from Summit Avenue to Weston Avenue including the Alderson/Weston Intersection.  Full closure to traffic from June 17, 2024 through August 30, 2024.
  2. Summit Avenue from Alderson Street to Wall Street. Full closure to traffic from August 28, 2024, through November 18, 2024.
  3. Weston Avenue from just east of the Alderson Intersection to Birch Street. Full closure to traffic from September 3, 2024, through November 18, 2024.