slider graphic

2020 Eagle Nest Boulevard/Tesch Lane Resurfacing Project

Due to the 2019-2020 weather conditions, the Village of Rothschild has decided that most of Eagle Nest Boulevard and all Tesch Lane will be milled and repaved. The Village would like to complete this immediately. Please see the image below for the project limits.

Eagles Nest

This work is tentatively scheduled to start Wednesday or Thursday, May 6 or 7, 2020. The work consists of removing, realigning, and replacing curb/gutter near the interseason of
Creske/Tesch Lane (south bound), and milling and re-paving 1.5" off the entire roadway (less median areas) from Stoney Rivers Drive to CTH XX.

The estimated road work schedule is as follows and is also weather dependent:

1) Week of 5/4/2020: Village will remove sections of curb/gutter and trail by the intersection of Tesch Lane. Areas will be excavated and replaced with base course.
2) Week of 5/11/2020.
    a) SD Ellenbecker will be replacing curb and gutter and drive approach.
    b) Merrill Sand and Gravel will be milling all the project area.
3) Week of 5/18/2020. Replacement of 1.5" of pavement by American Asphalt.

This work will require the partial and full road closures of Eagle Nest Boulevard and Tesch Lane. Alternate temporary accesses will need to be used by businesses during the window of construction. 

If there are unusual or extenuating circumstances, or if you have questions, please contact Tim Vergara at the Village Hall at 715-359-3660 or at tvergara@rothschildwi.com.